[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1034220":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},1034220,755,2,"多选题","需要系数法适用于（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","a.用电设备台数较多时；",true,{"key":16,"text":17,"correct":18},"B","b用电设备台数不多、功率悬殊时;",false,{"key":20,"text":21,"correct":14},"C","c.工业企业电力负荷计算；",{"key":23,"text":24,"correct":14},"D","d.工业企业照明负荷计算。","ACD","",{"id":6,"name":28,"category":29,"favorite":30},"电气工程师供配电专业","建筑工程",0]