[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1025762":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1025762,753,1,"单选题","对于改扩建项目的经济评价，以下表述中正确的是：",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","仅需要估算“有项目”、“无项目”、“增量”三种状态下的效益和费用",false,{"key":16,"text":17,"correct":14},"B","只对项目本身进行经济性评价，不考虑对既有企业的影响",{"key":19,"text":20,"correct":14},"C","财务分析一般只按项目一个层次进行财务分析",{"key":22,"text":23,"correct":24},"D","需要合理确定原有资产利用、停产损失和沉没成本",true,"提示 改扩建项目的经济评价应考虑原有资产的利用、停产损失和沉没成本等问题。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师公共基础(基础考试)","建筑工程",0]