[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1025722":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1025722,753,1,"单选题","对建设项目进行经济费用效益分析所使用的影子价格的正确含义是：",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","政府为保证国计民生为项目核定的指导价格",false,{"key":16,"text":17,"correct":14},"B","使项目产出品具有竞争力的价格",{"key":19,"text":20,"correct":14},"C","项目投入物和产出物的市场最低价格",{"key":22,"text":23,"correct":24},"D","反映项目投入物和产出物真实经济价值的价格",true,"提示 影子价格反映项目投入物和产出物的真实经济价值。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师公共基础(基础考试)","建筑工程",0]