[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1025690":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1025690,753,1,"单选题","某项目建设工期为两年，第一年投资200万元，第二年投资300万元，投产后每年净现金流量为150万元，项目计算期为10年，基准收益率10%，则此项目的财务净现值为：",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","331. 97 万元",false,{"key":16,"text":17,"correct":18},"B","188. 63 万元",true,{"key":20,"text":21,"correct":14},"C","171.18 万元",{"key":23,"text":24,"correct":14},"D","231. 60 万元","提示 按计算财务净现值的公式计算。FNPV=200-300(P\u002FF，10%，1) + 150 (P\u002FA,10%,8)(P\u002FF,10%,2) = -200-300X0. 90909 + 150X5. 33493X0. 82645 = 188. 63万元。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师公共基础(基础考试)","建筑工程",0]