[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1024768":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},1024768,751,2,"多选题","电气主接线的灵活性主要考虑（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","扩建灵活性；",true,{"key":16,"text":17,"correct":14},"B","调庋灵活性；",{"key":19,"text":20,"correct":21},"C","切换灵活性；",false,{"key":23,"text":24,"correct":14},"D","检修灵活性。","ABD","",{"id":6,"name":28,"category":29,"favorite":30},"电气工程师发输变电专业","建筑工程",0]