[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1024376":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},1024376,751,2,"多选题","水电厂最大负荷计算原则，下列描述正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","经常连续及不经常连续运行的负荷均应计算；",false,{"key":16,"text":17,"correct":18},"B","经常断续运行负荷应考虑同时率后计入；",true,{"key":20,"text":21,"correct":18},"C","互为备用的电动机，只计算参加运行的部分；当由不同变压器供电时，应分别计入；",{"key":23,"text":24,"correct":18},"D","不经常连续及不经常短时运行的负荷应按设备组合运行情况计算，但不计入仅在亊故情况下运行的负荷。","BCD","",{"id":6,"name":28,"category":29,"favorite":30},"电气工程师发输变电专业","建筑工程",0]