[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1024283":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},1024283,751,2,"多选题","对水电厂高压厂用电负荷的连接，说法正确的有（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","有地区电网但为扩大电厂的供电范围，从高压厂用电母线上引出近区用电回路；",false,{"key":16,"text":17,"correct":14},"B","有地区电网但为供电可靠，从高压厂用电母线上引出电厂生活用电回路；",{"key":19,"text":20,"correct":21},"C","厂用电高压电动机、坝区用电电源及低压厂用电变压器宜由高压厂用电母线上直接供电；",true,{"key":23,"text":24,"correct":21},"D","同一用途的高压电动机、低压厂用变压器应分别接至不同分段的髙压厂用电母线上，","CD","",{"id":6,"name":28,"category":29,"favorite":30},"电气工程师发输变电专业","建筑工程",0]