[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1024164":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},1024164,751,2,"多选题","发电机转子承受负序电流的能力，以I22为判据，（ ）应装设发电机转子表层过负荷保护。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","25MW及以上发电机A≥10的发电机；",false,{"key":16,"text":17,"correct":18},"B","50MW及以上发电机A≥10的发电机；",true,{"key":20,"text":21,"correct":14},"C","50MW及以上发电机A≤10的发电机；",{"key":23,"text":24,"correct":18},"D","100MW及以上发电机A 10的发电机。","BD","",{"id":6,"name":28,"category":29,"favorite":30},"电气工程师发输变电专业","建筑工程",0]