[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1024120":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},1024120,751,2,"多选题","并列运行的发电厂或电力系统之间，具有两条联系的线路或三条联系不紧密的线路，可采用（）重合闸方式。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","同步检定和无电压检定的三相重合闸方式；",true,{"key":16,"text":17,"correct":18},"B","不检同期的三相重合闸方式；",false,{"key":20,"text":21,"correct":14},"C","并列运行双回线路，也可采用栓查另一回线路有电流的自动重合闸方式；",{"key":23,"text":24,"correct":18},"D","解列重合闸方式，即将一侧电源解列，另一侧装设线路无电压检定的重合闸方式。","AC","",{"id":6,"name":28,"category":29,"favorite":30},"电气工程师发输变电专业","建筑工程",0]