[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023922":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},1023922,751,2,"多选题","对多支路非周期分量的计算，一般采用叠加法将时间常数类似的合并。一般，系统时间常数（Ta）较小，而发电机时间常数（Tb）较大，其范围为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","Ta≤13；",false,{"key":16,"text":17,"correct":14},"B","Ta≤14；",{"key":19,"text":20,"correct":21},"C","Ta≤15；",true,{"key":23,"text":24,"correct":21},"D","15≤Tb 80,","CD","",{"id":6,"name":28,"category":29,"favorite":30},"电气工程师发输变电专业","建筑工程",0]