[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023779":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1023779,751,1,"单选题","某电厂有3台50MW机组，发电机电压为10. 5kV，负荷要求地方10kV送电。当地 区负荷较少时，应将富余功率外送，系统电网为35kV及110kV，地区送电线要求10kV 12 回，高压各2回。 如果要求将发电机富余功率送入系统，升压变压器应（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设3台升压三绕組变压器；",false,{"key":16,"text":17,"correct":14},"B","设2台升压变压器至110kV,另设一台联络变压器；",{"key":19,"text":20,"correct":21},"C","设2台升压三绕组变压器；",true,{"key":23,"text":24,"correct":14},"D","设1台三绕组变压器，一台联络变压器。","按DL\u002FT 5000—2000 13.1.7条，如果要求将发电机富余功率送入系统，升压变压 器宜设2台升压三绕组变压器。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]