[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023774":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1023774,751,1,"单选题","发电机中性点的设计类型。 满足发电机中性点不接地方式的条件是（).",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发电机接地电流不超过允许值；",true,{"key":16,"text":17,"correct":18},"B","发电机中性点无避雷器；",false,{"key":20,"text":21,"correct":18},"C","125MW以上机组适用；",{"key":23,"text":24,"correct":18},"D","发电机直配线无避雷器。","根据《电力工程电气设计手册》（1)的相关规定： 第2-7节三、1.采用发电机中性点不接地方式的条件是：发电机接地电流不超过 允许值",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]