[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023771":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1023771,751,1,"单选题","某电厂装设4X200MW机组，有110kV及220kV升高电压，电厂潮流均应向两种 高压送电。 其发电机变压器宜采用的组合为（ )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","双绕组变压器、联络变压器；",true,{"key":16,"text":17,"correct":18},"B","三绕组变压器、联络变压器；",false,{"key":20,"text":21,"correct":18},"C","三绕组自耦变压器、联络变压器；",{"key":23,"text":24,"correct":18},"D","自耦变压器、联络变压器。","根据《火力发电厂设计技术规程》(DL\u002FT 5000——2000)的相关规定： 按DL\u002FT 5000—2000 13.1. 7明确容量为200MW及以上机组，不宜采用三绕组变 压器作升压变压器，如两种升高电压间需要联系时可设置联络变压器",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]