[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023767":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1023767,751,1,"单选题","某发电厂计划安装4台300MW机组，分期建设，发电机功率送入220kV系统， 220kV线路最终14回，采用少油断路器。 发电机升压变压器接人系统的方式为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发电机三绕组变压器组；",false,{"key":16,"text":17,"correct":18},"B","发电机双绕组变压器组；",true,{"key":20,"text":21,"correct":14},"C","扩大单元组;",{"key":23,"text":24,"correct":14},"D","发电机变压器线路组。","DL\u002FT 5000—2000 13.1. 7明确容量为200MW及以上机组，不宜采用三绕组变压 器作升压变压器，故本厂接入系统的方式应采用发电机双绕组变压器组接入系统。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]