[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023766":3},{"question":4,"library":22},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":15,"analysis":21},1023766,751,1,"单选题","某发电厂计划安装4台300MW机组，分期建设，发电机功率送入220kV系统， 220kV线路最终14回，采用少油断此厂应设（）台路器。 此厂应设（）台启动变压器。A. 1 台； B. 2 台;",[11,14,17,19],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":16},"B",true,{"key":18,"text":18,"correct":13},"C",{"key":20,"text":20,"correct":13},"D","DL\u002FT 5000—2000 13. 3.13中2规定：对容量300MW机组可按每两台机组设置一 台启动变压器台数，本厂应设置2台启动变压器",{"id":6,"name":23,"category":24,"favorite":25},"电气工程师发输变电专业","建筑工程",0]