[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023765":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1023765,751,1,"单选题","某发电厂计划安装4台300MW机组，分期建设，发电机功率送入220kV系统， 220kV线路最终14回，采用少油断路器。 根据规程其主接线采用（）方式。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单母线分段带旁路；",false,{"key":16,"text":17,"correct":14},"B","双母线带旁路；",{"key":19,"text":20,"correct":21},"C","双母线单分段带旁路；",true,{"key":23,"text":24,"correct":14},"D","单母线带旁路","根据《火力发电厂设计技术规程》(DL\u002FT 5000—2000) 13.2.12、13.1.7, 13. 3.13条 的规定： DL\u002FT 5000—2000 13. 2.12中2规定:对容量300MW机组，如发电厂装有3?4 台机组时，可采用双母线单分段接线，而采用了少油断路器故需增加旁路母线",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]