[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023745":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1023745,751,1,"单选题","4台容量为600MW的机组接入500kV系统，分两期建设。一期先建2X 600MW 的机组并有2回出线，二期工程将再扩建2X600MW的机组，主接线宜采用（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","双母线接线；",false,{"key":16,"text":17,"correct":14},"B","桥形接线；",{"key":19,"text":20,"correct":14},"C","四角形接线；",{"key":22,"text":23,"correct":24},"D","一台半断路器接线",true,"",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]