[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023684":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1023684,751,1,"单选题","地震动峰加速度超过( )的地区，配电装置设计应按有关的抗震规定采取抗震措施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.15g；",false,{"key":16,"text":17,"correct":18},"B","0.2g；",true,{"key":20,"text":21,"correct":14},"C","0.25g；",{"key":23,"text":24,"correct":14},"D","0.3g。","",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]