[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023664":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1023664,751,1,"单选题","某2X300MW火力发电厂厂用电系统采用6kV和380V两级电压，其中每台机组设 A、B两段6kV工作段，全厂设01 A、OlB两段6kV公用段，考虑公用段工作电源取自1、2号机组6kV工作段，备用电源取自启动\u002F备用变压器。见示意图9。每台机组设一台电动给水泵，都接于机组6kV工作A段，髙压厂用分裂变压器容量为：40\u002F25—25MVA（无载调压）。 若两台机组每段6kV工作段所连系统（包括髙压厂用变压器、封闭母线和电缆）对地电容基本相同，约为1.75μF,每段公用段所连系统对地电容基本相同，约为0.81μ F，试确定本工程6kV厂用电中心点的接地方式为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不接地；",true,{"key":16,"text":17,"correct":18},"B","高电阻接地；",false,{"key":20,"text":21,"correct":18},"C","消弧线圈接地；",{"key":23,"text":24,"correct":18},"D","直接接地。","解答过程： 根据《火力发电厂厂用电设计技术规定》（DL\u002FT5153—2002）4.2.1条，选择答案A。 又可见《电力工程电气设计手册》81页。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]