[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023628":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1023628,751,1,"单选题","某500kV变电站的建设规模如55题所述。变电站为有人值班，设有主控制室、500kV51小室、500kV52小室、220kV小室、主变压器小室。全站设置一套计算机监控系统实现监视、控制、远动等功能，监控系统的站控层设备布置在主控制室内，间隔层设备布置在各个小室内。请确定： 变电站计算机监控系统具有手动控制和自动控制两种控制方式，其中手动控制包括调度通信控制中心控制、站内主控制室控制、就地手动控制，其控制级别应是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","属于同一级别；",false,{"key":16,"text":17,"correct":18},"B","控制级别由高到低顺序为：就地、站内主控、远程调度中心；",true,{"key":20,"text":21,"correct":14},"C","控制级别由高到低顺序为：站内主控、就地、远程调度中心；",{"key":23,"text":24,"correct":14},"D","控制级别由高到低顺序为：远程调度中心、站内主控、就地。","解答过程： 根据DL\u002FT5149—2001第6.3.3条可判断B正确。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]