[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023626":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1023626,751,1,"单选题","某500kV变电站的建设规模如55题所述。变电站为有人值班，设有主控制室、500kV51小室、500kV52小室、220kV小室、主变压器小室。全站设置一套计算机监控系统实现监视、控制、远动等功能，监控系统的站控层设备布置在主控制室内，间隔层设备布置在各个小室内。请确定： 下列关于向监控系统站控层设备供电的UPS系统的描述中，正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","UPS宜采用单相式，输出电压为220V、50Hz,备用时间不小于1h；",true,{"key":16,"text":17,"correct":18},"B","UPS宜采用三相式，输出电压为220V、50Hz,备用时间不小于1h；",false,{"key":20,"text":21,"correct":18},"C","UPS宜采用单相式，输出电压为110V、50Hz,备用时间不小于2h；",{"key":23,"text":24,"correct":18},"D","UPS宜采用单相式，输出电压为220V、50Hz,备用时间不小于0.5h。","解答过程： 根据DL\u002FT5149—2001第10.1.2条可判断A正确。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]