[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023585":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1023585,751,1,"单选题","某300MW机组火力发电工程，主厂房设两台工作变压器，容量互为备用，设一段电动机控制中心（MC C）,变压器中性点直接接地?选择柴油发电机组时，事故保安A段计算负荷为435kVA,B段计算负荷为430kV A，重复计算负荷300kVA。接于PC和MCC的电负荷资料及厂用电接线见图5。 柴油发电机中性点接地方式应采用（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直接接地；",true,{"key":16,"text":17,"correct":18},"B","不接地；",false,{"key":20,"text":21,"correct":18},"C","高电阻接地；",{"key":23,"text":24,"correct":18},"D","低电阻接地。","解答过程： 根据《火力发电厂厂用电设计技术规定》（DL\u002FT5153-2002）第4.6.1条，交流保安电源的电压和中性点的接地方式宜与低压厂用电一致，故选A。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]