[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023584":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1023584,751,1,"单选题","某新建2X300MW火力发电厂，每台机组设 A、B两段6kV工作段，全厂设01 A、O1B两段6kV公用段，公用段间设有联络断路器，正常运行时公用段分别由I A、IIA单元段供电。每台机组设一台分裂绕组髙压工作变压器，容量50\u002F27-27MV A，半穿越阻抗U’ dl-2=21%,额定变比20±2X2.5%\u002F6.3—6.3kV。每台机组设一台备用电动给水泵，接于单元B段。发电机出口短路容量为4330MV A，每段6kV母线计算负荷及所接电动机额定功率之和如表3所示。 已知给水系电动机额定功率5500kW，启动电流倍数为6,电动机ηd?cosφd=0.8。髙厂变供电时，给水泵电动机正常启动时母线电压百分值为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","80.2%；",false,{"key":16,"text":17,"correct":18},"B","81.8%；",true,{"key":20,"text":21,"correct":14},"C","84.0%；",{"key":23,"text":24,"correct":14},"D","85.7%.","解答过程： 根据DL\u002FT5153—2002附录J计。注意给水泵起动前已带负荷为25400—5500=19900kVA，",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]