[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023578":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1023578,751,1,"单选题","某电厂装设4X300MW机组，有220kV及500kV升髙电压，电厂潮流均应向两种高压送电，其中1、2号机组接入220kV母线，3、4号机组接人500kV母线。220kV出线两回，500kV出线一回。 该电厂的启动\u002F备用电源从厂内220kV母线引接，且220kV配电装置采用双母线型式，则220kV断路器需要（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","6台；",true,{"key":16,"text":17,"correct":18},"B","7台；",false,{"key":20,"text":21,"correct":18},"C","8台；",{"key":23,"text":24,"correct":18},"D","9台，","解答过程： 根据DL\u002FT5000—2000第13.3.13条、13.3.14条规定。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]