[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023363":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1023363,751,1,"单选题","某500kV输电线路根据电气计算分析：500kV断路器变电所侧和线路侧的工频过电压倍数为最高相电压的1.3倍和1.4倍以下，但潜供电流大于12A以上，不能满足快速单相重合闸要求，需要考虑装设500kV高压并联电抗器。 采用装设高压并联电抗器措施可以降低本500kV输电线路的潜供电流水平，以实现快速单相重合闸保持系统稳定，下面对髙压并联电抗器（）说法是正确的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","应装设高压并联电抗器；",false,{"key":16,"text":17,"correct":14},"B","应装设中性点直接接地的高压并联电抗器；",{"key":19,"text":20,"correct":14},"C","应装设中性点经小电阻接地的高压并联电抗器；",{"key":22,"text":23,"correct":24},"D","应装设中性点经小电抗器接地并能补佳线路相间分布电容的高压并联电抗器。",true,"分析过程： 根据《电力系统技术导则》（SD131—1984试行）7.3节的相关规定。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]