[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023362":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1023362,751,1,"单选题","某500kV输电线路根据电气计算分析：500kV断路器变电所侧和线路侧的工频过电压倍数为最高相电压的1.3倍和1.4倍以下，但潜供电流大于12A以上，不能满足快速单相重合闸要求，需要考虑装设500kV高压并联电抗器。 在下列（）情况时不应该考虑装设髙压并联电抗器。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","线路断路器变电所侧和线路倒的工频过电压分别超过电网最高相电压的1.3倍和1.4倍时，需要采用快速单相重合闸保持系统稳定时；",false,{"key":16,"text":17,"correct":14},"B","发电厂和电网因无功平衡需要，而又不便装设低压并联电抗器时；",{"key":19,"text":20,"correct":14},"C","防止发电机自励磁和系统同期并列操作需要时；",{"key":22,"text":23,"correct":24},"D","限制电力系统短路电流需要时。",true,"分析过程： 根据《电力系统技术导则》（SD131—1984试行）7.3节的相关规定。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]