[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023361":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1023361,751,1,"单选题","已知某500kV受端地区系统，由于电源不足需要从外区经较长的500kV线路输入有功功率约1000MW,请分析回答以下问题： 受端系统应配置无功补偿设备总容量，下面（）不符合《电力系统电压和无功电力技术导则》（SD325—1989）要求。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","600Mvar；",true,{"key":16,"text":17,"correct":18},"B","450Mvar；",false,{"key":20,"text":21,"correct":18},"C","400Mvar；",{"key":23,"text":24,"correct":18},"D","500Mvar。","分析过程： 根据《电力系统电压和无功电力技术导则》（SD325—1989）5.2节的相关规定。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]