[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023360":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1023360,751,1,"单选题","已知某500kV受端地区系统，由于电源不足需要从外区经较长的500kV线路输入有功功率约1000MW,请分析回答以下问题： 受端系统如果按输入有功功率相应配置的无功补偿设备，其安装地点应选择以下（）方案.",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","安装在500kV变电所高压侧；",false,{"key":16,"text":17,"correct":14},"B","安装在500kV变电所220kV侧；",{"key":19,"text":20,"correct":14},"C","安装在受端系统某个220kV变电所；",{"key":22,"text":23,"correct":24},"D","分别安装在由其受端系统供电的220kV及以下变电所中。",true,"分析过程： 根据《电力系统电压和无功电力技术导则》（SD325—1989）5.2节的相关规定。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]