[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023357":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1023357,751,1,"单选题","某大型发电厂采用500kV电压等级，并经两回输电线路（线路主要数据：2X350km,LGJ-4X400mm2,每公里电抗为0.28Ω）向较强的受端电力系统送电，为了缩短输电线路的电气距离，以提高线路的输电能力和电力系统稳定性，根据规划论证决定在该输电工程中采用串联电容器补偿技术。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","过多（或过高）的串联电容补偿会引起发电机空载时自励磁现象，在某种运行方式下还将产生次同步谐振。根据《电力系统电压和无功电力技术导则》一般宜选用串联电容器补偿度不宜大于（）。",true,{"key":16,"text":17,"correct":18},"B","50%；",false,{"key":20,"text":21,"correct":18},"C","60%； C90%；",{"key":23,"text":24,"correct":18},"D","70%。","",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]