[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023350":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1023350,751,1,"单选题","为避免电力系统内线路发生永久性故障时系统失步可来用切发电机和切负荷，具体来说一般应该采用以下（）措施。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","在功率多余地区切除部分发电机，在功率不足地区不切除部分负荷；",false,{"key":16,"text":17,"correct":14},"B","在功率多余地区不切除发电机，在功率不足地区切除部分负荷；",{"key":19,"text":20,"correct":21},"C","在功率多余地区切除部分发电机，在功率不足地区切除部分负荷；",true,{"key":23,"text":24,"correct":14},"D","在功率多余地区投入部分发电机，在功率不足地区不切除部分负荷。","",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]