[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023347":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1023347,751,1,"单选题","以下（）不是电力系统静态稳定计算分析的目的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","确定电力系统稳定性；",false,{"key":16,"text":17,"correct":14},"B","确定输电线的输送功率极限；",{"key":19,"text":20,"correct":21},"C","核算振荡电流水平；",true,{"key":23,"text":24,"correct":14},"D","检验在给定运行方式下实际的静稳定储备。","",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]