[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023082":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1023082,751,1,"单选题","火力发电厂髙压厂用备用变压器或启动\u002F备用变压器容量选择，正确的一条是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","高压厂用启动\u002F备用变压器应不大于最小1台（组）高压厂用工作变压器的容量；",false,{"key":16,"text":17,"correct":14},"B","高压厂用启动\u002F备用变压器应不小于最小1台（组）和最大1台（组）高压厂用工作变压器平均容量；",{"key":19,"text":20,"correct":21},"C","高压厂用启动\u002F备用变压器应不小于最大1台（组）高压厂用工作变压器的容量；当启动\u002F备用变压器带有公用负荷时，其容量还应满足最大1台（组）高压厂用工作变压器备用要求；",true,{"key":23,"text":24,"correct":14},"D","对于单元制接线的发电机，当发电机出口装有断路器时高压厂用备用变压器的容量可为1台高压厂用工作变压器的50%。","",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]