[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023079":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1023079,751,1,"单选题","火力发电厂低压厂用备用变压器引接方式正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","低压厂用备用变压器宜与需要由其自动投入的低压厂用工作变压器接在同一髙压母线段上；",false,{"key":16,"text":17,"correct":18},"B","低压厂用备用变压器不宜与需要由其自动投入的低压厂用工作变压器接在同一高压母线段上；",true,{"key":20,"text":21,"correct":14},"C","C低压厂用工作变压器台数少于高压母线段数时，备用变压器可由任一高压母线段引接；",{"key":23,"text":24,"correct":14},"D","低压厂用备用变压器宜接至外部电网引接的可靠专用线路上。","",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]