[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023076":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1023076,751,1,"单选题","火力发电厂容量为600MW机组，高压厂用启动\u002F备用变压器设置条件中，正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","当发电机出口不装断路器或负荷开关时，每台机组应设1台启动\u002F备用变压器；",false,{"key":16,"text":17,"correct":18},"B","当发电机出口不装断路器或负荷开关时，每2台机组应设1台或2台启动\u002F备用变压器；",true,{"key":20,"text":21,"correct":14},"C","当发电机出口装有断路器或负荷开关时，3台及以下机組可设置1台高压启动\u002F备用变压器i",{"key":23,"text":24,"correct":14},"D","当发电机出口装有断路器或负荷开关时，5台及以下机组可设置1台高压启动\u002F备用变压器。","",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]