[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023075":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1023075,751,1,"单选题","火力发电厂容量为200~300MW机组，高压厂用启动\u002F备用变压器设置条件中，正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","高压厂用工作变压器数量在5台及以上可増设第2台髙压厂用启动\u002F备用变压器；",false,{"key":16,"text":17,"correct":14},"B","每3台机组可设1台高压厂用启动\u002F备用变压器；",{"key":19,"text":20,"correct":21},"C","每2台机组可设1台高压厂用启动\u002F备用变压器；",true,{"key":23,"text":24,"correct":14},"D","每台机組设1台高压厂用启动\u002F备用变压器。","",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]