[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1023032":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1023032,751,1,"单选题","关于火力发电厂负荷计算原则’下述不正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","连续运行的设备，应全部计算；",false,{"key":16,"text":17,"correct":14},"B","不经食短时及不经常断续运行的设备不予计算，但电抗器供电的应全部计算；",{"key":19,"text":20,"correct":21},"C","不同电源供电的互为备用设备，只计算运行部分；",true,{"key":23,"text":24,"correct":14},"D","对分裂电抗器运行的设备应分别计算每一臂电通过的负荷，不经常短时及不经常断续的设备不予计算。","",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]