[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022970":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1022970,751,1,"单选题","某电厂装设2X300MW汽轮发电机组，每台机组厂用高压6kV母线设2段母线，发电机电压为18kV，厂用工作变压器由发电机出口引接。 1、2号机组工作I A，IIA段计算负荷约为19730kVA,IB,IIB段母线计算负荷为1540kVA,2段6kV母线重复容量为3850kVA；若全厂公用负荷由启动\u002F备用变供电，设置2段母线，每段计算负荷各约5750kV A，6380kVA,则可选择的厂用髙压工作变压器形式和容量为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1台分裂变压器，容量40\u002F2020MVA；",false,{"key":16,"text":17,"correct":14},"B","2台双绕组变压器，容量均为20MVA；",{"key":19,"text":20,"correct":21},"C","1台分裂变压器，容量40\u002F2525MVA；",true,{"key":23,"text":24,"correct":14},"D","1台双绕组变压器，容量均为40MVA。","根据DL\u002FT 5153—2002第5.2.1条，厂用髙压工作变压器选1台分裂变压器，容量40\u002F25—25MVA，启动\u002F备用变检修时，全厂公用负荷由1、2号机组厂用高压工作变压器分担。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]