[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022969":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1022969,751,1,"单选题","某火电厂装有4台300MW机组，发电机电压为20kV,每台发电机以发电机变压器组接入500kV系统，500kV采用3\u002F2断路器接线，出线2回。 若电厂江边取水泵房距电厂5km，有6kV取水泵数台，对其可能的供电方式是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","由1号机组高压厂用工作母线经升压变压器引2回架空线路供电；",false,{"key":16,"text":17,"correct":14},"B","由3、4号机组各经升压器变压器引2回架空线路供电；",{"key":19,"text":20,"correct":21},"C","若公用段由1、2号启动\u002F备用变压器供电，也可由公用段经升压变压器引2回架空线路供电；",true,{"key":23,"text":24,"correct":14},"D","由厂内高压配电装置不同母线段引2回线路作工作电源和备用电源。","根据《火力发电厂厂用电设计技术规定》(DL\u002FT5153—2002)第5.3.2.4.7.1、4.7.4条。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]