[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022940":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1022940,751,1,"单选题","DL\u002FT5153-2002《火力发电厂厂用电设计技术规定》对短路电流计算和设备选择计算均做出了规定，请对下述各项作出判断。 低压厂用电系统短路电流计算应考虑的下述原则中，有误的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","应计及系统中的电阻；",false,{"key":16,"text":17,"correct":14},"B","低压厂用变压器高压側视为无穷大电源；",{"key":19,"text":20,"correct":21},"C","在动力中心的馈线短路时，应计及锖线回路阻抗，计及该馈线回路连接的异步电动机的反馈电流；",true,{"key":23,"text":24,"correct":14},"D","在动力中心和电动机控制中心内发生短路时，应计及连接在母线上的电动机反馈电流。","根据 DL\u002FT5153—2002第7.3.1条。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]