[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022938":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1022938,751,1,"单选题","DL\u002FT5153-2002《火力发电厂厂用电设计技术规定》对短路电流计算和设备选择计算均做出了规定，请对下述各项作出判断。 主保护动作时间与断路器固有分闸时间之和（）时，可不考虑高压厂用电短路电流非周期分量影响。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","大于0.11s；",false,{"key":16,"text":17,"correct":14},"B","0.11~0.15s之间；",{"key":19,"text":20,"correct":21},"C","大于0.15s；",true,{"key":23,"text":24,"correct":14},"D","不小于0.15s。","根据 DL\u002FT5153—2002第7.1.3条。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]