[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022928":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1022928,751,1,"单选题","某水力发电厂装机4 X200MW，均担任峰荷，每台机组均以发电机变压器组单元接线接入厂内110kV升压站，110kV出线4回与两个不同的220kV变电所110kV母线连接。设计中，厂用电确定了如下原则，哪些有误？请进行判断。 考虑相邻两台机组自用变压器互为备用，变压器容量应（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","每台自用变压器容量按两台机组全部I、II类负荷或短时满足最大负荷需要选择；",false,{"key":16,"text":17,"correct":14},"B","按带一台变压器正常运行负荷后，还应满足另一台变压器电动机自启动时的电压要求；",{"key":19,"text":20,"correct":14},"C","选择变压器容量时，不计温度修正系数的影响；",{"key":22,"text":23,"correct":24},"D","变压器的阻抗和容量选择庄满足空载自启动厂用母线电压不低于60%的要求。",true,"根据 DL\u002FT5164—2002第6.2.1、6.2.2、6.2.4、6.2.6条.",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]