[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022924":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1022924,751,1,"单选题","装机容量2X300MW火力发电厂设计中，需进行厂用电系统短路电流、电压调整、电动机启动时的电压校验等计算，其中： 电压调整计算中采用公式：Rt=1.1xPt\u002FS2t =1.1xUd%\u002FS2t中的数字1.1是考虑（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","变压器阻抗的正误差；",false,{"key":16,"text":17,"correct":14},"B","根据运行经验取的系数；",{"key":19,"text":20,"correct":21},"C","变压器空载电压与设备額定电压的差异；",true,{"key":23,"text":24,"correct":14},"D","A+C。","公式：Rt=1.1XPt\u002FS2t,及Xt=1.1Ud%\u002FS2t中的数字1.1是变压器空载电压与设备额定电压的差异，见DL\u002FT5153—2002附录H说明。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]