[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022922":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1022922,751,1,"单选题","某火力发电厂装有2X300MW机组，其低压厂用电采用380V，中性点经高电阻接地。 低压厂用电系统采用髙电阻接地方式时，热控配电箱、照明及检修系统的供电方式应作改变，下述说法有错的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","为热控配电箱需在动力中心馈线间隔内装设隔离变压器，变压器二次侧中性点直接接地；",true,{"key":16,"text":17,"correct":18},"B","宜设专用照明变压器，照明变压器可由髙压、低压厂用电母线供电，二次侧中性点直接接地。从低压厂用电系统引接的380V\u002F220V照明变压器，也可设分散设置；",false,{"key":20,"text":21,"correct":18},"C","在主厂房，检修电源宜从动力中心引接，并在检修配电箱内设置380V\u002F220V检修变压器；",{"key":23,"text":24,"correct":18},"D","每台600MW机组也可从专门设置一台检修变压器作检修电源，检修变压器同时作照明变压器的备用。","根据 DIVT5153—2002第4.7.10条。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]