[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022913":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1022913,751,1,"单选题","某火力发电厂装有4台600MW发电机组，每台机组设一台高压厂用分裂变压器向除脱硫系统以外的厂用负荷供电，每两台机组设一台启动\u002F备用分裂变压器，电源从厂外220kV系统引接。 若全厂公用负荷由1、2号机组高压厂用变压器供电时，启动\u002F备用变压器电源接线方式应至少为（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","一回线路，一台断路器；",false,{"key":16,"text":17,"correct":14},"B","一回线路，两台断路器；",{"key":19,"text":20,"correct":14},"C","两回线路，一台断路器；",{"key":22,"text":23,"correct":24},"D","两回线路，两台断路器。",true,"根据DL\u002FT5153—2002第4.5.3,9.2.2,9.5.1条。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]