[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022800":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1022800,751,1,"单选题","进行继电保护整定计算时，有3台及110kV变压器的双母线运行的发电厂，对变压器中性点接地方式的安排，正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","一般将1台变压器中性点接地运行；",false,{"key":16,"text":17,"correct":18},"B","一般将2台变压器中性点接地运行；",true,{"key":20,"text":21,"correct":14},"C","一般将3台变压器中性点接地运行；",{"key":23,"text":24,"correct":14},"D","一般将全部变压器中性点接地运行。","",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]