[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022763":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1022763,751,1,"单选题","某工程600MW发电机保护TA变比为25000\u002F5A, 5P20,发电机定子线电压为22kV,额定电流15746A,发电机次暂态电抗X\"d=18.26%，请根据上述已知条件回答下列有关定子绕组过负荷保护问题。 对定子绕组过负荷保护，下列说法正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定子绕组过负荷保护由定时限过负荷保护和反时限过电流保护组成；",true,{"key":16,"text":17,"correct":18},"B","定子绕组过负荷保护由定时限过负荷保护和过电流速断保护组成；",false,{"key":20,"text":21,"correct":18},"C","定时先负荷保护动作于信号或自动减负荷，反时限过电流保护动作于停机；",{"key":23,"text":24,"correct":18},"D","定时限过负荷保护动作于信号或自动减负荷，过电流速断保护动作于停机。","根据DL\u002FT 684—19994.5条的要求选择。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]