[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022740":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1022740,751,1,"单选题","200MW、15.75kV汽轮发电机宜装过电压保护。 保护动作时限一般取()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","O.2s；",false,{"key":16,"text":17,"correct":14},"B","0.4s；",{"key":19,"text":20,"correct":21},"C","O.5s；",true,{"key":23,"text":24,"correct":14},"D","0.6s?","根据DL\u002FT684—19994.8.4条的要求： 保护动作时间取0.5s。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]