[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022724":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1022724,751,1,"单选题","请回答电力系统安全稳定控制技术中的以下问题， 以下安全稳定控制措施中，第三道防线的控制措施是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","系统解列；",true,{"key":16,"text":17,"correct":18},"B","串联或并联电容强行补偿；",false,{"key":20,"text":21,"correct":18},"C","集中切负荷；",{"key":23,"text":24,"correct":18},"D","发电机励磁紧急控制，","根据DL\u002FT723—20004.2节的相关规定。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]