[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022678":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1022678,751,1,"单选题","系统电能计量关口点是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","省级电网之间的输电线路电量计量点；",true,{"key":16,"text":17,"correct":18},"B","省级电网和地区电网之间的输电线路电量计量点；",false,{"key":20,"text":21,"correct":18},"C","发电厂和电网之间的上网电量计量点；",{"key":23,"text":24,"correct":18},"D","地区电网及其用户之间的高压输配电线路电量计量点。","",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]