[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022664":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1022664,751,1,"单选题","与负荷变化相适应的调整速度一般要求为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","火电机组每分钟1.5%，水电机组45%额定容量以上；",false,{"key":16,"text":17,"correct":14},"B","火电机組每分钟1%,水电机组40%額定容量以上；",{"key":19,"text":20,"correct":21},"C","火电机组每分钟2%,水电机组50%額定容量以上；",true,{"key":23,"text":24,"correct":14},"D","火电机组每分钟1.75%,水电机组40%額定容量以上。","",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]